Building management

BMS testing and commissioning: a practical checklist for handover

Commissioning is where a BMS stops being a set of controllers and starts running the building. This is what each stage should prove before you sign the handover.

Many BMS complaints after handover trace back to the same cause: commissioning was rushed. Sensors read the wrong value, a valve is reversed, a standby pump never starts. Good commissioning finds these problems while the contractor is still on site.

Use this checklist to plan commissioning or to review a contractor’s method statement.

Before commissioning starts

  • Mechanical and electrical systems are installed, flushed, powered and safe to run.
  • Controllers are installed, powered and on the network with the approved addresses.
  • The approved points schedule and sequence of operation are available on site.
  • Test sheets are prepared for every system, with space for signatures.

Starting before the plant is ready is the most common reason commissioning drags on. Agree a readiness checklist with the MEP contractor first.

Stage 1: point-to-point checks

Every hardwired point is tested from the field device to the BMS graphic.

  • Inputs: compare each sensor reading with a calibrated instrument; check status signals by operating the equipment.
  • Outputs: command each valve, damper and starter and confirm the device moves the right way and the full range.
  • Labels: confirm the point name, units and location on the graphic match the schedule.

Stage 2: integrated points

For chillers, drives, meters and other equipment read over BACnet or Modbus, compare BMS values with the equipment display. Check scaling, units and alarm states. Command any writable values and confirm the equipment responds.

Stage 3: sequence and functional tests

This is the heart of commissioning. Each sequence of operation is tested under real or simulated conditions:

  • start and stop sequences, including time schedules and occupancy,
  • control loops: temperature, pressure, humidity and CO2, with stable response,
  • duty, standby and rotation of pumps and fans, including failover on a trip,
  • plant staging, such as chiller and pump sequencing,
  • safeties and interlocks, such as freeze or high-temperature protection and fire alarm shutdown signals.

For chilled water plants, staging and reset strategies deserve their own attention. See chiller plant optimisation with a BMS.

  • Trigger each alarm and confirm priority, message and acknowledgement.
  • Check that trend logs record at the agreed intervals and are stored long enough.
  • Generate the energy and runtime reports in the specification.

Stage 5: witness testing

The consultant or owner’s engineer witnesses a sample, or all, of the tests. Prepare by running the tests first without witnesses, fixing issues, and only then booking the witness session. Record every comment and close them before the handover meeting.

Handover documents

  • Signed test sheets for every stage
  • As-built drawings and the final points schedule
  • Controller programs, database backups and licence details
  • Final sequence of operation
  • O&M manuals and training records

After handover: seasonal checks

Some issues only appear under peak summer load. A review of trends after the first hot months, with sequence tuning where needed, is good practice and often part of a maintenance contract.

Synthronix commissions the BMS systems it installs and also re-commissions existing systems that never worked as intended. See our BMS service for details.

FAQ

Common questions.

Not covered here? Ask an engineer

What is point-to-point testing in a BMS?

It is the check that every physical point works end to end. That means the field sensor or device, its cable, the controller input or output, and the value shown on the BMS graphic. Each point is tested and signed on a sheet.

Who attends BMS witness testing?

Usually the consultant or the owner’s engineer, the main or MEP contractor, the BMS contractor and sometimes the facility management team. The witness test confirms that sequences work as specified.

How long should BMS commissioning take?

It depends on the number of points and systems, and on whether the mechanical plant is ready. Commissioning cannot be completed while chillers, AHUs or pumps are still being installed, so it should be planned with the MEP programme.

Keep reading

All articles

Talk to an engineer

Need help with Building Management Systems?

Send drawings, a BOQ or photos of the existing system. Our engineers review it and reply with the next step.

Step 1 of 2 · Your project

Your project
Project type
Your details

Your details go only to our engineering team. Privacy policy