Many BMS complaints after handover trace back to the same cause: commissioning was rushed. Sensors read the wrong value, a valve is reversed, a standby pump never starts. Good commissioning finds these problems while the contractor is still on site.
Use this checklist to plan commissioning or to review a contractor’s method statement.
Before commissioning starts
- Mechanical and electrical systems are installed, flushed, powered and safe to run.
- Controllers are installed, powered and on the network with the approved addresses.
- The approved points schedule and sequence of operation are available on site.
- Test sheets are prepared for every system, with space for signatures.
Starting before the plant is ready is the most common reason commissioning drags on. Agree a readiness checklist with the MEP contractor first.
Stage 1: point-to-point checks
Every hardwired point is tested from the field device to the BMS graphic.
- Inputs: compare each sensor reading with a calibrated instrument; check status signals by operating the equipment.
- Outputs: command each valve, damper and starter and confirm the device moves the right way and the full range.
- Labels: confirm the point name, units and location on the graphic match the schedule.
Stage 2: integrated points
For chillers, drives, meters and other equipment read over BACnet or Modbus, compare BMS values with the equipment display. Check scaling, units and alarm states. Command any writable values and confirm the equipment responds.
Stage 3: sequence and functional tests
This is the heart of commissioning. Each sequence of operation is tested under real or simulated conditions:
- start and stop sequences, including time schedules and occupancy,
- control loops: temperature, pressure, humidity and CO2, with stable response,
- duty, standby and rotation of pumps and fans, including failover on a trip,
- plant staging, such as chiller and pump sequencing,
- safeties and interlocks, such as freeze or high-temperature protection and fire alarm shutdown signals.
For chilled water plants, staging and reset strategies deserve their own attention. See chiller plant optimisation with a BMS.
Stage 4: alarms, trends and reports
- Trigger each alarm and confirm priority, message and acknowledgement.
- Check that trend logs record at the agreed intervals and are stored long enough.
- Generate the energy and runtime reports in the specification.
Stage 5: witness testing
The consultant or owner’s engineer witnesses a sample, or all, of the tests. Prepare by running the tests first without witnesses, fixing issues, and only then booking the witness session. Record every comment and close them before the handover meeting.
Handover documents
- Signed test sheets for every stage
- As-built drawings and the final points schedule
- Controller programs, database backups and licence details
- Final sequence of operation
- O&M manuals and training records
After handover: seasonal checks
Some issues only appear under peak summer load. A review of trends after the first hot months, with sequence tuning where needed, is good practice and often part of a maintenance contract.
Synthronix commissions the BMS systems it installs and also re-commissions existing systems that never worked as intended. See our BMS service for details.